Highlights

  • Brennan Construction will continue working in Bedford Hills through the beginning of September, including low-pressure service connections on School Street.

 

  • Coordination is underway with regulatory agencies for final testing and startup of sewer pump stations.

Bedford Hills – Katonah Business Sewer District

August 16 – September 2, 2021

Construction

  •  All sewer pipe and manholes have been installed leading into the wastewater treatment plant.
  • Brennan has completed the installation of water services and sewer laterals on Babbitt Road.
  • Installation of sewer main and manholes at St. Mary’s has been completed.

Progress Summaries 8/16/21- 9/2/21

  • Startup at Pump Station A occurred including a walk through with Department of Health. There are a few items that need to be finalized, but this station will be ready to be put into service soon.
  • Brennan continued installing sewer pipe and manholes at St. Mary’s leading up to the existing manhole.
  • Brennan began installation of the 2-inch low-pressure sewer main on School Street.
  • Brennan has completed the installation of manholes and sewer main near the wastewater treatment plant and completed asphalt restoration of the area

Upcoming Work

  • Department of Health will be onsite for startup and walk through of Pump Station B next week before the pump station is put into service.
  • Continue installation of the 2-inch low-pressure sewer main and service connections on School Steet. The crew will then relocate to Edgemont Road and Woods Bridge Road to begin low-pressure sewer main installation.