Highlights
- Brennan Construction will
continue working in Katonah through the
end of September, including lowpressure service
connections on Woods Bridge Road. - Coordination is underway with regulatory agencies
for final approval and startup of sewer pump stations
Bedford Hills – Katonah Business Sewer District
September 10, 2021
Construction
- All low-pressure sewer pipe and manholes have been installed on School Street
Progress Summaries
- Brennan completed remaining site restoration work at Pump Station A required for final Department of Health approval so this pump station will be ready to be put into service soon.
- Department of Health walkthrough took place at Pump Station B. Remaining site work will be finalized next week so this pump station will also be ready to be put into service.
- Brennan began installation of the 2-inch low-pressure sewer main on Edgemont Road turning onto Woods Bridge Road.
Upcoming Work
- Brennan will begin site layout at the Bedford Park Apartment Pump Station.
- The crew will continue installation of the 2-inch low-pressure sewer main and service
connections on Woods Bridge Road.