Highlights

 

  • Brennan Construction will continue working in the Bedford Hills Business District through Mid-July, including water service replacement on Babbitt Road.
  • Coordination is underway with regulatory agencies for final testing and startup of sewer pump stations this summer.

Bedford Hills – Katonah Business Sewer District

July 7, 2021

Construction

  • The construction crew has continued sewer main and manhole installation on Main Street.

Progress Summaries              

  • Sewer main and manhole installation has continued on Main Street with approximately 78 linear feet of sewer pipe installed this week. The crew encountered unexpected rock, so progress has been slower than usual.

Upcoming Work

  • Brennan will continue sewer main and manhole installation on Main Street next week. The service laterals will be installed once sewer main and manhole installation is complete.
  • After work is completed on Main Street, Brennan will then complete water service work, sewer main and manhole installation on Babbitt Road.