Highlights

 

  • Brennan Construction will continue working in the Bedford Hills Business District through Mid-August, including water service replacement on Babbitt Road.
  • Coordination is underway with regulatory agencies for final testing and startup of sewer pump stations this summer.

Bedford Hills – Katonah Business Sewer District

July 30, 2021

Construction

  • The construction crew has completed sewer main, manhole, and service lateral installation on Main Street.

Progress Summaries

  • Brennan began sewer main and manhole installation on Babbitt Road with approximately 140 linear feet of pipe installed this week.
  • A smaller crew began sewer lateral work at St. Mary’s in advance of paving.
  • Approximately 45 linear feet of pipe was installed near the Bedford Park Apartments in preparation of upcoming painting of the Metro North fence posts.

Upcoming Work

  • The construction crew will continue sewer main and manhole installation on Babbitt Road and then install sewer laterals and water services.
  • Installation will begin next week for the low pressure sewer services on Adams Street so the section between Harris Road and School Street can be paved by the Town.