Highlights

  • Brennan Construction will continue working in Bedford Hills through mid-August, including water service replacement on Babbitt Road.  

 

  • Coordination is underway with regulatory agencies for final testing and startup of sewer pump stations.
  •  

Bedford Hills – Katonah Business Sewer District

August 13, 2021

Construction

  • All gravity sewer with the exception of the Bedford Park Apartments has been installed.

Progress Summaries              

  • Brennan has continued to install water services and sewer laterals on Babbitt Road. Progress has been slower than anticipated due to existing utilities in the area.
  • Brennan has continued to install manholes and sewer pipe near the wastewater treatment plant.
  • The influent screen has been installed at the wastewater treatment plant.
  • Gas and electric work was completed at Pump Station A and Pump Station B in preparation of upcoming startup.

Upcoming Work

  • Startup at Pump Station A and Pump Station B is planned for Friday, August 20.
  • The crew on Babbitt Road will continue installing the remaining water services and sewer laterals. This crew will then work on asphalt restoration of Babbitt Road.
  • Brennan will continue installing manholes and sewer pipe near the wastewater treatment plant. The crew will then work on asphalt restoration on Beaver Dam Road.