    • Brennan Construction continues to make great progress. Crews will continue to work in tandem to expedite project progress.

    • Brennan Construction anticipates finishing almost all work in the Katonah Hamlet within the next month.

Bedford Hills – Katonah Business Sewer District

September 25, 2020

Construction

  • Sewer pipe and manhole installation work continued on Valley Road working west towards New Street.
  • Crews continued with sewer pipe, both force main sewer and gravity sewer, as well as manhole installation on Bedford Road.

Progress Summaries              

  • Approximately 200 linear feet of force main sewer pipe installed on Bedford Road.
  • Approximately 200 linear feet of gravity sewer pipe and one manhole was installed on Bedford Road.
  • Approximately 85 linear feet of sewer was installed on Valley Road.
  • Temporary pavement was placed on Bedford Road.

Upcoming Work

  • Contractor will continue to install sewer pipes and manholes on Bedford Road, working south towards Congdon Lane.
  • Work will continue on Valley Road and make the turn to New Street. There are no property sewer laterals along this sewer alignment.