Highlights

 

    • Brennan Construction continues to make great progress. Crews will continue to work in tandem to expedite project progress.
    • Brennan Construction will not be working on Labor Day, Monday, September 7

Bedford Hills – Katonah Business Sewer District

August 28, 2020

 

Construction

  • Sewer pipe and manhole installation work continued on Valley Road working west towards New Street.
  • Crews continued with sewer pipe and manhole installation on Allen Place, working south onto Bedford Road.

Progress Summaries              

  • Approximately 120 linear feet of sewer pipe on Valley Road.
  • Lateral connection was installed for the following properties: 55 Bedford Road, 68 Bedford Road, 71 Bedford Road, and 73-77 Bedford Road.
  • Culvert replacement on Valley Road is complete.
  • Approximately 74 linear feet of sewer pipe was installed Bedford Road.
  • Temporary asphalt pavement was placed on Allen Place and Valley Road.

Upcoming Work

  • Contractor will continue to install sewer pipes and manholes on Bedford Road, including service laterals. Upcoming laterals include: 80 & 87 Bedford Road
  • Work will continue on Valley Road, working west towards New Street.