Highlights

 

    • Brennan Construction continues to make great progress. Crews will continue to work in tandem to expedite project progress
      .
    • Brennan Construction is planning to finish up work in the Katonah hamlet this summer.
    • It is anticipated that the project will continue to be ahead of schedule.

Bedford Hills – Katonah Business Sewer District

July 24, 2020

Construction

  • Sewer pipe installation continued on Katonah Avenue and is nearly complete.
  • Sewer pipe and manhole installation work occurred on Valley Road working west from Bedford Road.
  • Contractor continues with sewer work on Katonah Avenue.

Progress Summaries

  • Approximately 34 linear feet of sewer was installed on Katonah Avenue.
  • Approximately 250 linear feet of gravity sewer was installed on Valley Road.
  • Temporary pavement was placed on Katonah Avenue.

Upcoming Work

  • Contractor plans to continue with sewer pipe and manhole installation on Valley Road working towards Bedford Road.
  • Work will start on Allen Place, working west towards Bedford Road.
Traducir al español

Stay Informed

Join our mailing list and receive newsletters, reports and emergency updates.

You have Successfully Subscribed!