Highlights

 

  • Brennan Construction continues to make great progress. Crews will continue to work in tandem to expedite project progress.
  • Brennan Construction is hopeful to finish up work in the Katonah hamlet this summer.
  • It is anticipated that the project will continue to be ahead of schedule.
  • The Contractor will not be working on Friday, July 3.

Bedford Hills – Katonah Business Sewer District

July 2, 2020

Construction

  • The Contractor continued with installation of sewer pipe and manholes on The Parkway.
  • The Contractor performed pre-testing of pipes and manholes in advance of Westchester County Department of Health testing.
  • Pump Station A sheeting was removed.

Progress Summaries              

  • Approximately 120 linear feet of sewer was installed on The Parkway.
  • Temporary pavement was placed on The Parkway.

Upcoming Work

  • Complete sewer installation work on the Parkway and water service work.
  • Sewer construction work continue on The Parkway next week.
  • Construction to start on Valley Road tentatively July 13th.