Highlights

  • Brennan Construction continues to make great progress. Crews will continue to work in tandem to expedite project progress.
  • Brennan Construction is hopeful to finish up work in the Katonah hamlet this summer.
  • It is anticipated that the project will continue to be ahead of schedule.
  • The Contractor is beginning work at 6:00 AM but future work on Valley Road/New Street and Huntville Road would begin at 8:00 AM.

Bedford Hills – Katonah Business Sewer District

June 19, 2020

 

    • Construction

      • The Contractor continued work on Katonah Avenue, with some water main service work as well as the placement of temporary pavement.
      • The Contractor began sewer installation on Edgemont Road.
      • Pump Station B was delivered and installed in Bedford Hills.
      • The contractor continues to excavate for Pump Station A in Katonah.

      Progress Summaries              

      • Work on Edgemont Road continues. Approximately 140 linear feet of sewer pipe was installed.
      • Temporary pavement was placed on Katonah Avenue as well as Huntville Road, in front of Katonah Elementary School.
      • One of the three pump stations included in this project have been installed.

      Upcoming Work

      • Pump Station A excavation to continue next week, with delivery of second pump station next week.
      • Sewer construction work continue and shift to The Parkway next week.