Highlights

  • There will be no work on Memorial Day, 5/31/2021
  • Brennan Construction will continue working in the Bedford Hills Business District in early June
  • Brennan Construction continues to make good progress, remaining on track for completion in summer 2021

Bedford Hills – Katonah Business Sewer District

May 28, 2021

Construction

  • Crew continues to work on Adams Street, working south towards Route 117.
  • The second crew continued gravity sewer manhole and pipe installation on Griffin Avenue.

Progress Summaries              

  • Brennan continued installation of sewer pipe and manholes on Adams with approximately 155 linear feet of pipe and one manhole installed this week.
  • Sewer pipe and manhole installation continued on Griffin Avenue with approximately 95 linear feet of pipe and one manhole installed this week.
  • Asphalt paving took place at various project areas in preparation for the holiday weekend.

Upcoming Work

  • Brennan will continue to work on Adams Street, working towards Route 117.
  • Brennan will continue to work on Griffin Avenue, working towards Babbitt Road.