Highlights

  • Brennan Construction will be working in Bedford Hills Business District in early May
  • Brennan Construction continues to make good progress, remaining on track for completion in summer 2021

 

Bedford Hills – Katonah Business Sewer District

May 7, 2021

Construction

      • Force main installation continued on Beaver Dam Road.
      • Vaults are being installed for the force main on Harris Road.

Progress Summaries              

      • Brennan continued force main installation on Beaver Dam Road with approximately 50 linear feet of force main installed this week.
      • Force Main Cleanout Vaults M1 and L4 were installed on Harris Road.
      • Laterals were installed on Valley Road.

Upcoming Work

      • Brennan will continue installing force main cleanout vaults on Harris Road. This crew will then relocate to begin work on Adams Street in Bedford Hills.
      • Brennan will install the remaining gravity laterals that remain on Valley Road. This crew will then begin setting equipment for the Bedford Park Apartment Pump Station.