Highlights

  • Brennan Construction will be working in Bedford Hills Business District in early May
  • Brennan Construction continues to make good progress, remaining on track for completion in summer 2021

 

Bedford Hills – Katonah Business Sewer District

April 16, 2021

Construction

  • Brennan completed force main installation on Adams Street at the intersection of Harris Road and completed paving, so all of Adams Street between Pump Station B and Harris Road has been completed with the exception of School Street.
  • Force main installation continued on Babbitt Road.
  • Brennan has completed installing the remaining laterals in Katonah.

Progress Summaries              

  • Brennan completed work at the intersection of Adams Street and Harris Road and began force main installation on Harris Road with approximately 190 linear feet of force main installed this week.
  • Force main installation continued on Babbitt Road with approximately 205 linear feet of force main installed this week.
  • Manhole Vault L1 was installed on Babbitt Road.

Upcoming Work

  • Brennan will continue sewer pipe and manhole installation heading south on Harris Road.
  • Brennan will continue with force main installation on Babbitt Road, working north toward Harris Road.