Highlights

  • Brennan Construction will be working in Bedford Hills Business District in early May
  • Brennan Construction continues to make good progress, remaining on track for completion in summer 2021

 

Bedford Hills – Katonah Business Sewer District

April 23, 2021

Construction

  • Force main installation continued on Harris Road and on Babbitt Road.
  • Horizontal directional drilling of force main pipe was completed under the Broad Brook.

Progress Summaries              

  • Brennan continued force main installation on Harris Road with approximately 200 linear feet of force main installed this week.
  • Force main installation continued on Babbitt Road with approximately 350 linear feet of force main installed this week.
  • Roadway restoration took place on Harris Road, Valley Road, and Babbitt Road.

Upcoming Work

  • Brennan will continue sewer pipe and manhole installation heading south on Harris Road and will make the turn onto Beaver Dam Road.
  • Brennan will continue with force main installation on Babbitt Road, working north toward Harris Road.
  • Brennan will install the remaining gravity laterals that remain on Valley Road and Bedford Road.