  • Brennan Construction continues to make great progress. Crews will continue to work in tandem to expedite project progress.
  • Brennan Construction anticipates finishing almost all work in the Katonah Hamlet this month, and will be working down Bedford Road, and Harris Road, towards Bedford Hills.

Bedford Hills – Katonah Business Sewer District

October 9, 2020

Construction

  • Sewer pipe and manhole installation work continued on New Street, working towards Huntville Road.
  • Crews continued with sewer pipe, both force main sewer and gravity sewer, as well as manhole installation on Bedford Road.

Progress Summaries              

  • Approximately 110 linear feet of force main sewer pipe was installed on Bedford Road.
  • Approximately 200 linear feet of gravity sewer pipe and two manholes were installed on Bedford Road.
  • Approximately 142 linear feet of sewer and one manhole was installed on New Street.
  • Temporary pavement was placed on New Street.
  • Lateral for 105 Bedford Road was installed.

Upcoming Work

  • Contractor will continue to install sewer pipes and manholes on Bedford Road, working south towards Congdon Lane. Building lateral for 122-138 Bedford Road will be installed soon.
  • Work will continue on New Street, working south towards Huntville Road.