Highlights

 

  • Following the installation of Bedford Park Apartment Pump Station this month, sewer installation will continue towards Bedford Hills with work occurring on Babbitt Road & downtown Bedford Hills
  • There are some remaining sewer laterals that will be installed in Katonah in the Spring
  • Brennan Construction continues to make good progress, remaining on track for completion in early summer 2021

Bedford Hills – Katonah Business Sewer District

January 15, 2021

Construction

  • The installation of sewer pipe on Huntville Road has been completed.
  • Crews are preparing for the installation of a new pump station at the Bedford Park Apartments on January 20th.
  • Force main has been installed on Adams Street, and will continue heading south toward Bedford Hills.

Progress Summaries              

  • Force main installation continued on Adams Street with approximately 400 linear feet of sewer pipe installed this week.
  • Brennan is preparing erosion control measures at the Bedford Park Apartments in preparation for the pump station installation.
  • Contractors began electrical work at Pump Station B for the upcoming installation of the control panel and generator.

Upcoming Work

  • Work will continue with low pressure sewer installation on Adams Street, moving south toward Bedford Hills.
  • Brennan will continue with electrical work at Pump Station B.
  • Brennan will install the pump station at the Bedford Park Apartments on January 20th.
Traducir al español

 Stay Informed

Join our mailing list and receive newsletters, reports and emergency updates.

You have Successfully Subscribed!